UPDATE AS OF 8/10/20
Past 2 weeks
Sports Pavilion
- continue vinyl
- install backboards
- complete sanitary fixtures
- hang doors and hardware
- fit off lights
- hook up storm water tank
Town Square
Commence digging holes for decking stumps
S-HUB
- complete structural steel
- complete battening roof
- install new roof flashings and capping
- commence rough in
- commence timber framing
Next 2 weeks
Sports Pavilion Install roller door Commence ply wall lining
Town Square
- Form up and pour CN03
- Continue decks
S-HUB
- Commence window frames
- Continue rough in
- Concrete infills
- Commence floor leveling
UPDATE AS OF 22/10/20
Past 2 weeks
Sports Pavilion
- Commence ply wall lining
- Commence decanting of site
Town Square
- Form up and pour CN03
- Continue decks
- Dig and pour bollard and light pole footings
S-HUB
- Continue rough in hydraulic
- Continue rough in Elec and data
- complete rough in Mechanical
- Concrete infills
Next 2 weeks
Sports Pavilion
- Install roller door
- Complete ply walls
- Install nets
- Commence sports floor
Town Square
- Continue CN03
- Continue decks
- Install lighting
S-HUB
- complete services rough in
- commence floor rectifications
- commence floor grind
- commence windows and doors