Past 2 weeks
Sports Pavilion
- Install roller door
- Continue ply walls
- Install nets
- Commence sports floor
Town Square
- Complete CN03
- Continue decks
- Install bollard lighting
- Prep for asphalt reinstatement
S-HUB
- Complete services rough in
- Commence floor rectifications
- Commence floor grind
Next 2 weeks
Sports Pavilion
- Complete ply wall lining
- Continue timber sports floor
Town Square
- Electrical fit off
- Continue decks
- Commence services variation works
S-HUB
- Commence windows and door install
- Continue floor grind and prep
- Measure op walls
- Complete security